Beyond the backlash: Building trust when infrastructure divides

Authors: Meha Bola, Romina Cavallo, Lauren Harding and Andrew Porter
ATM-18_slide-4.jpg Open cut mining tailings dam

At a glance

Following the Accredited Technical Masterclass Beyond the Backlash: Building trust when infrastructure divides, this page brings together the questions raised during the session alongside the responses shared by GHD's technical specialists. The discussion explored common community engagement challenges project teams encounter s when delivering infrastructure projects. It provides practical insights into how to address social opposition and how to overcome trust-gaps when a relationship breakdown has occurred. 

Following the Accredited Technical Masterclass Beyond the backlash: Building trust when infrastructure divides, this page brings together the questions raised during the session alongside the responses shared by GHD's technical specialists.

Your questions answered

1) How do you gain trust and support of residents who will, in the short term, be affected by a major sewer capacity upgrade project in their residential street and close to their houses/backyards but in long term will serve tens of thousands of residents?

This is a classic fairness challenge we see frequently, particularly on linear infrastructure projects. A few households carry the disruption while the benefit is spread across tens of thousands of residents. We recommend openly acknowledging the impact on local residents, rather than relying only on the "greater good".

Talk to affected residents one-on-one, and do it early, while their feedback can still influence decisions such as construction methods. Be clear about what is fixed (the need and the route) and explain why. Then offer real choices on what is open to input, such as work hours, access, noise controls and how gardens or driveways will be restored.

Give residents a single contact person, keep them informed throughout and follow up once the works are finished. Where possible, explore local benefits and legacy opportunities, for example, can footpaths and parks be improved? Can you invest in local priorities and needs?

2) How do we determine when continued involvement in a controversial project is consistent with our professional and ethical responsibilities, and when it may be appropriate to step back?

This is a challenge we can really relate to. When we're in a community-facing role, we hear directly from communities about their concerns and worries, and we listen with empathy. Part of our job is to see things from their perspective and bring those perspectives into project decisions where possible. 

Something we find helpful is to remind ourselves that controversy doesn't automatically mean a project is “bad”. Some people will inevitably be more affected by a project than others. A project team's responsibility is to understand who is affected and how, and to explore how those impacts can be avoided or managed.

The question to ask ourselves is whether the process is fair. Can communities genuinely influence something? Are impacts being acknowledged honestly?Will commitments be kept? It may be time to step back if you're asked to mislead people, hide known impacts or run engagement that only seeks endorsement for a decision that's already been made.

If you have concerns, raise them internally first, frame them as a project risk, and use your professional and company codes of conduct as your reference point. Often, staying involved is how we help a project do better, so stepping back should be a last resort, not the first response.

3) What approaches have you found effective when working with internal stakeholders who have competing operational priorities, particularly when you need information or input from them within specific timeframes to meet project deadlines?

The SCARF model (Status, Certainty, Autonomy, Relatedness, Fairness) works inside organisations too. Involve internal teams early when setting timelines so the deadlines are agreed, not imposed (autonomy and fairness). Be specific about what you need, when and why, and make it easy to provide (certainty). 

Link the request to delivery risk, such as delay, cost or a community issue escalating, so it can be prioritised among other shared organisational priorities (increasing relatedness). 

Build relationships before you need something (relatedness) and get a senior sponsor to back the timeframe when needed (status). Close the loop by showing how their input was used (certainty) and what difference it made (status).

4) The Muskoka bin site project highlights project delays. How do you offset the costs associated with project delays emerging from engagement activities?

It's a fair question. Good engagement does take time and money. But in our experience, engagement isn't usually the cause of delays. It tends to expose risks that were already there.

In Muskoka, working through each site individually took longer than transitioning them all at once. But it built the acceptance the district needed to make the change stick. The FORTAG example shared was similar: the changes cost more and took longer, but the team, the client and the community all agreed the project was better for it. The alternative is often unresolved opposition, which can lead to legal challenges, political escalation, redesign and reputational damage. Those usually cost far more.

To manage cost, build engagement into the program and budget from day one, and match its depth to the level of risk. Start while the design can still change. Where you can, stage delivery so lower-risk elements keep moving while the harder ones are worked through.

5) Of the SCARF elements, what do you think is missing in the current debate about data centres in Australia?

Fairness and certainty stand out.

The debate tends to focus on the national economic case, while local communities are worried about whether a data centre will use their water, push up their power bills or create constant noise. When the benefits feel national and the impacts feel local, fairness quickly becomes the issue.

Certainty is also low. Communities want clear, plain-language answers about water and energy use. But those answers depend heavily on design choices, and early on they’re often not available, or not shared.

Autonomy and relatedness matter too, particularly where approvals feel fast-tracked or proponents are new to the area.

What helps close these gaps is to find out what people are worried about, design to reduce those impacts where you can, then go back and tell the community what changed, and ask how they feel about it.

6) We all know early communication builds trust and helps the process, but our contracts prevent us from going to the wider community until all landholders have signed. So, what is the answer?

There’s no perfect answer, but there are ways to reduce the risk.

First, landholders are community too. Engage them deeply and respectfully, because how they’re treated will shape the wider story. Be aware that landholder payments can create "haves and have nots", dividing those who benefit from neighbours who carry the impacts without compensation. Neighbour or community benefit arrangements can help share benefits more widely.

Second, talk with the client about the risk of silence. A knowledge vacuum is quickly filled by rumour and word of mouth, and it can deepen that divide between those who’ve signed and those who haven’t. With the client’s agreement, see whether general information can be shared early about the need, the process, the timing and how benefits will be shared, without site-specific details.

Third, have the wider engagement ready to launch the moment you can. When you do go public, be candid about why the timing was what it was. Being honest about the constraint helps rebuild certainty and fairness.

7) If you have a project that’s already run into a high level of community issues, can it be course corrected?  Appreciating it’s better to start on a better footing, what one or two points would you suggest for a project that’s already facing opposition? Is it ever too late?

Yes, it can be course corrected, and it is rarely too late, though it gets harder the longer distrust is left to harden. 

Three points: 

  1. Stop and listen: acknowledge what hasn't worked and work out whether you are dealing with a knowledge gap or a trust gap. More information won’t fix a trust gap, but who provides it matters. An independent expert chosen by the community can help rebuild trust in the project information being shared. 
  2. Make a visible change: identify what is genuinely open, act on community input and show people exactly what changed because of them, for example, through design changes and before-and-after images. 
  3. Having an independent SME chosen by the community might also be a good way to rebuild trust in the project information being shared.

Remember to accept that the aim is a credible process, not universal agreement.

8) What approach would you recommend where the client relies on the subcontractor to develop the trust but it might be an afterthought and actually erode trust?

Trust is a whole-of-project responsibility. Subcontractors can do much of the day-to-day relationship work, but accountability can’t be handed over. Communities usually hold the client responsible, whoever is on site.

The strongest approach is an overarching organisational engagement strategy that all contractors align to. It sets clear expectations and a consistent way of managing community issues, including shared key messages, a single commitments register and one complaints process.

To stop engagement becoming an afterthought, build it in from the start. Include these requirements in contracts and scopes, define roles clearly and raise any gaps early with the client as a delivery risk, not just a communication issue.

Subcontractors can then do the relationship work well, supported by a consistent framework and a client whose leaders stay visible and accountable in the community.

9) What mistakes do companies most commonly make when seeking a social licence to operate in remote communities, and what does the evidence suggest works better?

Common mistakes include turning up only when you need something, fly-in fly-out engagement, relying on one-off donations and offering jobs that locals can’t actually access. Others are assuming more information will resolve concerns, treating First Nations communities as stakeholders rather than rights holders, and not following through on commitments.

What works better is getting to know the community before asking for anything, keeping a long-term and consistent presence and being open to shaping the project in response to community feedback. 

Capacity building is also important. Remote communities often have few resources and staff with other priorities, as well as dealing with several proponents at once. Funding the community to get its own independent advice, and paying for people's time to take part, can support them to engage on an equal footing and make informed decisions. 

10) How do you manage community engagement, regulatory requirements and a divide between these two stakeholders? 

Regulatory requirements are meant to represent and protect the best interests of the community. Be clear with communities about what the regulator sets (fixed), what is open to their input and how their feedback will (or will not) inform the regulatory process. 

Where community expectations go beyond regulatory minimums, consider whether it is advantageous to make the investment go further, for example, with extra mitigation or additional features that increase benefits returned to the community. 

Share community insights with regulators so they understand the local context and bring them into the conversation with the community where appropriate. Being the honest broker between both sides helps maintain trust in the process even when people disagree with the content.

11) Most common trigger for community opposition: feeling the decision has already been made. How can we address this appropriately?

This is a clear threat to autonomy and showed up as a key concern in the poll during the Accredited Technical Masterclass. Falling participation can be an early sign that people believe the decision is already made and disengage. 

If possible, engage before key decisions are locked in. Where something is fixed, say so and explain why, including the criteria and history behind the decision. Then identify what is genuinely open, such as design features, mitigation, timing or local benefits, and give people real opportunities to influence those elements. 

Even when core technical requirements are fixed, other elements like open space, landscaping and public art can often be shaped by and with the community. Finally, close the loop by showing how community input changed the outcome and explaining why when it didn’t. 

12) What strategies can you use to mitigate deliberate misinformation about the project from bad actors?

First, separate deliberate misinformation (i.e., misinformation) from genuine concern. Most people repeating a claim are worried, not bad actors, and should be treated with empathy and respect. While it is always the right move to provide correct information, you should manage your expectations in changing people’s position on a project. 

The goal should be to reach those who want accurate information and have not yet taken a strong position in favour of or opposed to the project. Be candid about what is unknown, because overclaiming or inaccuracy damages credibility. 

Neighbours and local groups carry more weight than institutions, so work through trusted local messengers and independent experts or reviews. Monitor the channels where the conversation is happening, correct the facts calmly and avoid amplifying bad actors by debating them on their terms. Focus on the wider community, keep a visible presence and let consistent follow-through do the persuading.

13) How do we create internal buy-in for a shift from “explaining and defending” to “listening and understanding”? Is there a risk that teams may be interpreting that shift as criticism of their expertise or previous approach?

This is a real risk. It is a status threat in SCARF terms, so how you frame the shift matters. Position listening as adding to technical expertise, not replacing it. A strong technical case still matters, but on its own it won’t build confidence. 

Frame it as delivery risk management (delay, cost, reputation), which speaks to project teams’ priorities. Use evidence to show the benefits. Acknowledge that previous approaches must be adjusted to suit a different trust environment. Bring engineers and designers into community sessions so they hear community concerns first-hand. Have senior leaders model the behaviour and celebrate wins where listening led to a better project or outcome.

14) How can we invite engagement during critical or urgent work, when there isn’t much room for compromise?

When there is little room to compromise, focus on certainty and relatedness. Tell people early and clearly what is happening, why it is urgent, when it will happen and how long it will last. Be honest that the work itself isn’t negotiable and explain why. Then look for the choices that are still open, such as timing, access arrangements, noise controls or how people are notified, and let the community shape those. Provide a single contact person, acknowledge the disruption and follow up afterwards. Relationships built before urgent works give you goodwill to draw on when time is short.

15) All the response sets are outward looking, i.e., it’s not us, it’s them. But is it?

A fair challenge, and no, it is not just them, it is also us. Feeling the decision has already been made, not being heard or taken seriously, distrust of the proponent or government, and unfair sharing of impacts and benefits all describe how organisations behave, not how communities react. Even concerns about project impacts and cumulative pressures depend on how we avoid, manage and share those impacts. A trust gap is often a response to how organisations have behaved in the past.

16) What are your thoughts on cumulative opposition where there is absolutely no impact from the project on the submitter?

These submissions are still worth understanding. Opposition from people with no direct impact often reflects values, fairness concerns or wider distrust of institutions and the planning system. That is the 'language broadens' warning sign. It may also reflect fatigue from multiple projects in the same region or larger social trends. Treat it as intelligence about the wider trust environment rather than dismissing it. 

Decision-makers can reasonably weigh it differently from the views of directly affected people. But be transparent about how all submissions are considered. Respond to the underlying themes, not just individual points, and keep your main focus on the people who carry the impacts.

17) What is the role of government in supporting community engagement between proponents and communities? How can they support good outcomes for the project and build community trust?

Government has an important role in setting the conditions for trust, because it’s expected to act in the public interest.

Government can explain the strategic need for programs such as the energy transition, so individual proponents aren’t left making that case alone. It can set clear, consistent expectations for engagement and benefit sharing, and make timely decisions that reduce uncertainty for everyone involved.

Both local and state government are well placed to coordinate across projects, working collaboratively with proponents to help manage cumulative impacts and community fatigue. One idea that we would like to see in Australia is one-stop-shops (particularly in renewable energy zones) where communities can find information about all the projects in their region.

Government can also hold proponents to their commitments, and support independent mechanisms, such as an infrastructure commissioner or ombudsman, that communities can turn to when issues aren’t resolved. Being visibly present in communities, not just at the approval stage, helps too.

When government and proponents give consistent messages, communities are more likely to see the process as fair.

18) Clients often worry that early community engagement may give organised opposition groups an opportunity to shape public narratives. How do you approach this concern while still delivering meaningful, early engagement?

It is a common concern, but staying silent rarely stops opposition. It just leaves an information vacuum that others fill first. 

Early engagement lets you set the context, explain the problem being solved and share accurate information before narratives form. Start with the need and the options, not a finished solution, and be honest about what is still unknown. 
Engage broadly so you hear from those who are directly impacted, as well as the wider community, not just the loudest voices. 

Opposition also gives you useful information and it is far better to learn about concerns while the design can still change. Document what you hear and show how it shaped the project. That visible follow-through is your strongest defence against misleading narratives.

19) How do you recommend maintaining trust and engagement when a project goes on hold or is otherwise paused?

Tell people promptly and honestly. Silence during a pause is often read as a decision already made, or as something being hidden. Explain why the project is paused, what it means for them and when they can next expect an update, even if that update is “no news yet”.

Keep a contact person available and keep honouring any commitments already made, such as property repairs or community support. Where you can, keep up local relationships and benefits that don’t depend on the project going ahead.

When the project restarts, don’t assume earlier support still holds. Acknowledge the gap, check what has changed in the community and explain what has changed in the project. A pause handled well can build trust, because it shows you communicate even when the news is uncertain.

20) How do you deal with misinformation? It seems to be more widespread with the emergence of social media, etc.?

Social media has made misinformation faster and harder to contain, so speed and presence matter. Be first with clear, plain-language information, and keep a single, easy-to-find source of truth, such as a project webpage with FAQs that are updated regularly.

Who shares the information matters as much as what it says. Our communities tend to trust their neighbours, local groups and independent experts more than a project or organisation. Work with trusted local sources, such as councils, community groups, local businesses or respected community members to share accurate information through the channels people already use. An independent expert or review, ideally one the community has a say in choosing, can also help settle contested questions.

Anticipate the likely myths and address them early, before they spread. Respond to the concern behind a claim, not just the claim itself. 

21) How can you regain trust when you have lost it?

Start by acknowledging specifically what went wrong and taking responsibility, without being defensive. Then work out what actually broke trust. Was it a broken promise, a decision people had no say in or an impact that wasn’t taken seriously? The fix needs to match the cause.

From there, make small, clear commitments and keep every one of them. Consistent follow-through over time does more than any single gesture. Giving the community some control can help too, for example, through a community reference group or an independent review.

Be patient and watch the direction of trust; do not expect it to turnaround quickly. Some community members may never fully return, and that's okay. The aim is a process people can see is fair.

22) Do you have any tips on mitigating misinformation in the comment section despite all your efforts to educate the community and efforts for trying to build trust?

Remember who your real audience is. Many community members reading a comment section never post (close to 90 percent), so your replies are really for them, not the person making the claim.

Post clear community guidelines upfront and moderate consistently. Remove abuse and personal attacks, but not disagreement, because deleting critical comments can look like there is something to hide or be silenced.

Reply once, calmly, with the facts and a link to a trusted source. That could be an independent report, a council or agency page or a local specialist. Try to minimise links back to your own project materials. Then step back, because long back-and-forth arguments tend to amplify the claim.

Over time, the most effective corrections often come from others in the community. People who have been involved in the project, such as reference group members or local business owners, are often more credible in a comment thread than the project team. Where someone seems genuinely concerned, invite them to talk directly.

23) How do you manage people’s short-term priorities when they are in conflict with long-term community benefits? 

This is one of the hardest challenges, and it is a very human reaction. Immediate impacts feel real and personal, while long-term benefits feel abstract and uncertain and may not even benefit those who are experiencing the impact.

It helps to make the long-term impacts local and tangible. Take the short-term impacts seriously too. Reduce these where you can and support or compensate those who carry them, because fairness is often the real issue.

Adaptive or staged approaches, with clear trigger points, can reduce what people are asked to accept today.

Broaden whose voice is heard. Representative methods, such as randomly recruited focus groups or community panels, show decision-makers what the wider community thinks, not just the most vocal or well-connected. That gives decision makers firmer ground for long-term decisions.

24) Once construction ends, how do you check with residents that the project delivered the benefits that mattered most to them?

The key is to go back to what people told you mattered at the start, and check against that, not against what the project team assumes was important.

Revisit the same people and groups you engaged with early on, including any community reference group. Repeat some of the original survey questions so you can compare before and after responses. Close out the commitments register publicly, showing what was delivered, what changed and why.

Walking the site with residents could be a good approach, because they'll tell you quickly what is working and what isn’t. Then report back on what you heard and what you'll do about any gaps.

Ideally, this is planned and budgeted from the start, so it isn’t dropped once the construction team moves on